Caltrans Logo

San Gabriel Valley Park&Ride

Description: Construction of a four-level parking structure with 511 parking spaces.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City West Covina
Zip Code 91790
 
Senate District
30
Assembly District 59
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5    100  
Reduced Emissions      90  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RUBEN CERVANTES (626) 931-7231   RCERVANTES@FOOTHILLTRANSIT.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $51 $51
PTMISEA-99314
$3,271 $0 $3,271
Non-bond Funding
State/Federal*
$14,574 $50,414 $64,988
Local**
$0 $5,793 $5,793
 
Total**** $17,846 $56,258 $74,103

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$600 $700 $1,300 $0 $0 $1,300
Design(PS&E)
$1,200 $300 $1,500 $121 $121 $1,379
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$16,046 $55,258 $71,303 $3,201 $3,201 $68,102
 
Total* $17,846 $56,258 $74,103 $3,322 $3,322 $70,781

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2011 

04/01/2012 
09/20/2010 

09/20/2010 
07/01/2011 

04/01/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2012 

01/01/2013 
09/20/2010 

03/07/2013 
05/01/2012 

10/01/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/01/2013 

08/01/2014 
03/07/2013 

09/27/2013 
10/01/2012 

12/01/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2014 

11/01/2014 
05/09/2017 

05/09/2017 
06/01/2016 

03/01/2017 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5 100
Reduced Emissions 90

Bond Funding Cost
Adopted:
$3,271,166
Current Approved:
$3,271,166
Actual Expenditures:
$3,271,166

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31