Replacement Alternative Fuel Buses

Description: Purchase of up to 199 New Flyer CNG buses including 16 Electric Buses.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City West Covina
Zip Code 91790
 
Senate District
24
Assembly District 57
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  15      
Reduced Emissions  15      
Reduced Operating/Maintenance Cost  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RUBEN CERVANTES (626) 931-7231   RCERVANTES@FOOTHILLTRANSIT.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $181 $181
PTMISEA-99314
$2,874 $13,416 $16,290
Non-bond Funding
State/Federal*
$9,523 $35,977 $45,500
Local**
$3,387 $5,469 $8,856
 
Total**** $15,784 $55,043 $70,827

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$15,784 $55,043 $70,827 $70,828 $70,828 $-0
 
Total* $15,784 $55,043 $70,827 $70,828 $70,828 $-0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2012 

06/30/2012 
08/20/2014 

10/27/2021 
12/01/2014 

08/01/2021 
86   

 


Begin Closeout Phase

End Closeout Phase
03/01/2012 

06/30/2012 
10/27/2021 

10/27/2021 
08/01/2021 

08/30/2021 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 15
Reduced Emissions 15
Reduced Operating/Maintenance Cost 15

Bond Funding Cost
Adopted:
$2,874,046
Current Approved:
$16,290,400
Actual Expenditures:
$16,290,400

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31