Caltrans Logo

CNG Vehicle Refueling Station and Facility Shop Upgrades

Description: Construction of a CNG vehicle refueling station and transportation facility improvements.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Norwalk
Zip Code 90650
 
Senate District
30
Assembly District 56
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  50      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
THERESA CLARK (562) 929-5601   TCLARK@CI.NORWALK.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99314
$199 $505 $704
Non-bond Funding
State/Federal*
$550 $2,248 $2,798
 
Total**** $749 $2,753 $3,501

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$749 $2,753 $3,501 $707 $707 $2,794
 
Total* $749 $2,753 $3,501 $707 $707 $2,794

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2008 

09/01/2008 
07/22/2010 

07/22/2010 
04/01/2008 

07/01/2008 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2008 

12/01/2008 
07/26/2013 

07/26/2013 
09/01/2010 

05/01/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/01/2009 

05/01/2009 
09/11/2013 

09/11/2013 
09/01/2013 

10/01/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2009 

07/01/2009 
08/13/2015 

08/13/2015 
01/01/2015 

03/01/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50

Bond Funding Cost
Adopted:
$198,612
Current Approved:
$703,797
Actual Expenditures:
$703,797

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31