Caltrans Logo

Pacheco Transit Hub

Description: Project is to fund the construction of a six-bay transit hub at the intersection of Highway 680 and State Route 4

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa
City Concord
Zip Code 94520
 
Senate District
11
Assembly District 07
Congressional District 10
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  10    3  
Reduced Emissions      1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
CELINDA DAHLGREN (925) 676-1976   CDAHLGREN@CCCTA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$800 $-270 $530
Non-bond Funding
Local**
$1,732 $336 $2,068
 
Total**** $2,532 $66 $2,598

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$643 $-1 $642 $642 $642 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,889 $67 $1,956 $1,956 $1,956 $0
 
Total* $2,532 $66 $2,598 $2,598 $2,598 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2006 

08/01/2008 
 

 
01/01/2007 

03/01/2007 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/01/2006 

09/01/2008 
 

02/21/2013 
06/01/2007 

01/01/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2009 

02/01/2009 
02/25/2014 

09/09/2014 
09/01/2013 

09/01/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2009 

08/01/2009 
09/09/2014 

09/09/2014 
10/01/2014 

12/31/2014 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 10 3
Reduced Emissions 1

Bond Funding Cost
Adopted:
$800,000
Current Approved:
$529,970
Actual Expenditures:
$529,970

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31