PCJPB South Terminal Station Project |
Description: Platform Construction at San Jose Diridon and Maintenance Facility Removal
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Clara |
City | San Carlos |
Zip Code | 94070 |
Senate District |
08, 11, 13 |
Assembly District | 12, 19, 21, 22, 23, 24, 27 |
Congressional District | 08, 12, 14, 15, 16 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 10 | 10 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
REBECCA ARTHUR | (650) 508-6368 | ARTHURR@SAMTRANS.COM |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $7 | $7 | ||||
PTMISEA-99314 |
$6,850 | $-6,830 | $20 | ||||
Non-bond Funding | |||||||
State/Federal* |
$36,832 | $-5,264 | $31,568 | ||||
Local** |
$8,318 | $-5,543 | $2,776 | ||||
Total**** | $52,000 | $-17,630 | $34,370 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$1,750 | $-1,750 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$6,950 | $4,518 | $11,468 | $11,468 | $11,468 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$43,300 | $-20,398 | $22,902 | $22,902 | $22,902 | $0 | |
Total* | $52,000 | $-17,630 | $34,370 | $34,370 | $34,370 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
04/23/2007 11/01/2007 |
04/25/2011 04/25/2011 |
04/23/2007 11/08/2007 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/23/2007 12/31/2008 |
04/25/2011 04/25/2011 |
04/23/2007 04/30/2009 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
04/01/2008 11/26/2008 |
|
04/01/2008 11/26/2008 |
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
12/04/2008 08/31/2011 |
11/15/2011 03/07/2013 |
12/03/2009 08/31/2012 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
09/01/2011 03/31/2012 |
03/07/2013 03/07/2013 |
09/01/2012 06/30/2013 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 10 | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$6,849,847 |
Current Approved: |
$19,865 |
Actual Expenditures: |
$19,865 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31