Signal Optimization

Description: Design, procure, and install new train signal communication system at Redwood City and San Mateo

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City San Carlos
Zip Code 94070
 
Senate District
12, 19, 21, 22, 23, 24
Assembly District 08, 11, 13
Congressional District 08, 12, 14, 15, 16
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
PETER SKINNER (650) 622-7818   SKINNERP@SAMTRANS.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$400 $0 $400
Non-bond Funding
State/Federal*
$1,600 $0 $1,600
 
Total**** $2,000 $0 $2,000

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,000 $0 $2,000 $2,000 $2,000 $0
 
Total* $2,000 $0 $2,000 $2,000 $2,000 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/2011 

09/30/2011 
 

 
06/30/2011 

09/30/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/04/2011 

03/30/2012 
02/26/2013 

08/20/2013 
10/22/2012 

04/30/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2012 

10/01/2012 
08/20/2013 

08/27/2014 
05/01/2013 

06/30/2014 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 10

Bond Funding Cost
Adopted:
$400,000
Current Approved:
$400,000
Actual Expenditures:
$400,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31