Caltrans Logo

BART Balboa Park Station Improvements

Description: Project is to construct a safe and accessible walkway located along the west side of the Balboa Parl BART station.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City Oakland
Zip Code 94604
 
Senate District
03, 07, 08, 09, 10
Assembly District 09, 11, 12, 13, 14, 16
Congressional District 09
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability        
Increased Ridership      1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MR. MICHAEL S. TANNER (510) 464-6443   MTANNER@BART.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$1,154 $0 $1,154
Non-bond Funding
State/Federal*
$2,840 $-2,088 $752
Local**
$242 $3,141 $3,383
 
Total**** $4,236 $1,054 $5,289

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$71 $-71 $0 $0 $0 $0
Design(PS&E)
$320 $480 $800 $800 $800 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,845 $644 $4,489 $4,489 $4,489 $0
 
Total* $4,236 $1,054 $5,289 $5,289 $5,289 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2005 

08/01/2006 
03/27/2012 

03/27/2012 
08/01/2010 

05/31/2011 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/01/2006 

07/11/2008 
03/27/2012 

03/05/2014 
10/01/2010 

02/28/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/01/2009 

02/01/2009 
07/06/2020 

07/06/2020 
09/01/2015 

09/30/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
02/01/2010 

12/01/2010 
07/06/2020 

07/06/2020 
07/01/2019 

06/30/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability
Increased Ridership 1

Bond Funding Cost
Adopted:
$1,153,610
Current Approved:
$1,153,610
Actual Expenditures:
$1,153,610

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31