Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
City of Fresno/FAX/Paratransit Facility |
Description: Fresno Area Express (FAX) is proposing to purchase property that includes the space and structures needed to appropriately house its paratransit equipment and operations.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Fresno |
City | Fresno |
Zip Code | 93706 |
Senate District |
14, 16 |
Assembly District | 31 |
Congressional District | 20 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | 3 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
Darlene Christiansen | (559) 621-1469 | Darlene.Christiansen@FRESNO.GOV |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2024 b=c-a |
Current Approved (12/31/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$2,143 | $200 | $2,343 | ||||
PTMISEA-99314 |
$1,057 | $-255 | $802 | ||||
Non-bond Funding | |||||||
Total**** | $3,200 | $-55 | $3,145 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2024 b=c-a |
Current Approved (12/31/2024 c |
Cost to Date** (12/31/2024 d |
Cost Forecast (12/31/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$200 | $-200 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$3,000 | $145 | $3,145 | $3,145 | $3,145 | $0 | |
Total* | $3,200 | $-55 | $3,145 | $3,145 | $3,145 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2024) c |
% Complete (12/31/2024) d |
Schedule Forecast (12/31/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
05/01/2009 06/30/2009 |
02/15/2011 02/15/2011 |
07/01/2010 12/31/2010 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/01/2009 09/30/2009 |
09/13/2011 09/29/2015 |
11/01/2010 07/31/2016 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/01/2009 09/30/2010 |
09/13/2011 09/29/2015 |
05/01/2011 11/30/2016 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
09/01/2010 11/30/2010 |
08/12/2019 08/12/2019 |
12/31/2017 02/01/2018 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | 3 |
Bond Funding Cost | |
---|---|
Adopted: |
$3,199,912 |
Current Approved: |
$3,145,017 |
Actual Expenditures: |
$3,145,017 |
Status as of December 31, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31