Caltrans Logo

Bus Shelters Purchase

Description: Purchase of 2 bus shelters at bus stops along California City Blvd

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City California City
Zip Code 93505
 
Senate District
18
Assembly District 34
Congressional District 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  3      
Reduced Emissions  2      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MIKE BEVINS (760) 373-7297   PWDIR@CALIFORNIACITY.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$11 $0 $11
Non-bond Funding
 
Total**** $11 $0 $11

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$11 $0 $11 $11 $11 $0
 
Total* $11 $0 $11 $11 $11 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2010 

11/30/2010 
04/15/2014 

04/15/2014 
02/01/2012 

03/31/2012 
 

 


Begin Closeout Phase

End Closeout Phase
11/01/2010 

08/31/2011 
04/15/2014 

04/15/2014 
03/01/2014 

03/31/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 3
Reduced Emissions 2

Bond Funding Cost
Adopted:
$10,763
Current Approved:
$10,763
Actual Expenditures:
$10,763

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31