Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Westway Station -- Multi-Modal Transit Center |
Description: To construct a multi-modal transit center at the southwest corner of California City Blvd and Wonder Ave.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Kern |
City | California City |
Zip Code | 93505 |
Senate District |
18 |
Assembly District | 34 |
Congressional District | 22 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | |
Increased Ridership | 10 | |
Reduced Emissions | 4 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
MIKE BEVINS | (760) 373-7297 | PWDIR@CALIFORNIACITY.COM |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$575 | $-27 | $548 | ||||
PTMISEA-99314 |
$9 | $0 | $9 | ||||
Non-bond Funding | |||||||
Total**** | $584 | $-27 | $558 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$52 | $0 | $52 | $71 | $71 | $-19 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$532 | $-27 | $505 | $486 | $486 | $19 | |
Total* | $584 | $-27 | $558 | $558 | $558 | $-0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/01/2010 09/30/2011 |
08/04/2014 |
06/01/2010 08/31/2012 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2011 11/30/2011 |
08/04/2014 08/04/2014 |
09/01/2012 12/31/2012 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/01/2012 03/31/2012 |
08/04/2014 08/04/2014 |
02/01/2013 08/31/2013 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
03/01/2012 05/31/2012 |
08/04/2014 08/04/2014 |
08/01/2013 10/31/2013 |
100 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | |
Increased Ridership | 10 | |
Reduced Emissions | 4 |
Bond Funding Cost | |
---|---|
Adopted: |
$584,382 |
Current Approved: |
$557,576 |
Actual Expenditures: |
$557,576 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31