Westway Station -- Multi-Modal Transit Center

Description: To construct a multi-modal transit center at the southwest corner of California City Blvd and Wonder Ave.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City California City
Zip Code 93505
 
Senate District
18
Assembly District 34
Congressional District 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      5  
Increased Ridership  10      
Reduced Emissions  4      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MIKE BEVINS (760) 373-7297   PWDIR@CALIFORNIACITY.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$575 $-27 $548
PTMISEA-99314
$9 $0 $9
Non-bond Funding
 
Total**** $584 $-27 $558

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$52 $0 $52 $71 $71 $-19
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$532 $-27 $505 $486 $486 $19
 
Total* $584 $-27 $558 $558 $558 $-0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2010 

09/30/2011 
 

08/04/2014 
06/01/2010 

08/31/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2011 

11/30/2011 
08/04/2014 

08/04/2014 
09/01/2012 

12/31/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2012 

03/31/2012 
08/04/2014 

08/04/2014 
02/01/2013 

08/31/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
03/01/2012 

05/31/2012 
08/04/2014 

08/04/2014 
08/01/2013 

10/31/2013 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5
Increased Ridership 10
Reduced Emissions 4

Bond Funding Cost
Adopted:
$584,382
Current Approved:
$557,576
Actual Expenditures:
$557,576

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31