Caltrans Logo

Handicap Doors

Description: Provide a hassle free entrance for ADA customers by installing ADA accessible doors

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings
City Corcoran
Zip Code 93212
 
Senate District
16
Assembly District 30
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability        
Increased Ridership  2      
Reduced Operating/Maintenance Cost  2    30  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
STEVE KROEKER (559) 992-2151   STEVE.KROEKER@CITYOFCORCORAN.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$0 $11 $11
PTMISEA-99314
$3 $9 $12
Non-bond Funding
 
Total**** $3 $21 $24

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3 $21 $24 $24 $24 $0
 
Total* $3 $21 $24 $24 $24 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2010 

12/01/2010 
 

 
10/01/2010 

12/01/2010 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/03/2011 

02/04/2011 
 

 
01/03/2011 

02/04/2011 
 

 


Begin Right of Way Phase

End Right of Way Phase
02/07/2011 

04/01/2011 
 

 
02/07/2011 

04/01/2011 
 

 


Begin Construction Phase

End Construction Phase
04/29/2011 

06/06/2011 
11/21/2011 

11/21/2011 
11/01/2012 

12/01/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
 

07/29/2011 
11/21/2011 

11/21/2011 
12/01/2012 

01/31/2013 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability
Increased Ridership 2
Reduced Operating/Maintenance Cost 2 30

Bond Funding Cost
Adopted:
$3,015
Current Approved:
$23,856
Actual Expenditures:
$23,856

Click to view the Semi-Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31