Transit/Vehicle Maintenance Yard Gate

Description: Install automatic security gate and lighting at the transit/vehicle maintenance yard

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Mariposa
City Mariposa
Zip Code 95338
 
Senate District
12
Assembly District 25
Congressional District 19
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  100      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DANA S. HERTFELDER (209) 966-5356   DHERTFELDER@MARIPOSACOUNTY.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $3 $3
PTMISEA-99313
$118 $-3 $115
PTMISEA-99314
$2 $0 $2
Non-bond Funding
 
Total**** $120 $-1 $119

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$120 $-1 $119 $119 $119 $0
 
Total* $120 $-1 $119 $119 $119 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

04/01/2009 
08/25/2011 

09/07/2012 
06/01/2011 

01/31/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2009 

08/01/2009 
09/07/2012 

09/07/2012 
02/28/2012 

08/30/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
08/01/2009 

09/01/2009 
09/07/2012 

02/21/2013 
09/01/2012 

12/01/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 100

Bond Funding Cost
Adopted:
$120,000
Current Approved:
$119,203
Actual Expenditures:
$119,203

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31