Caltrans Logo

Purchase & Installation of Bus Shelters

Description: Purchase & Installation of Bus Shelters throughout Merced County

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Merced
City Merced
Zip Code 95340
 
Senate District
12
Assembly District 17
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  2      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ROD GHEARING (209) 385-7600   RGHEARING@CO.MERCED.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $20 $20
PTMISEA-99313
$61 $41 $102
PTMISEA-99314
$0 $24 $24
Non-bond Funding
Local**
$0 $83 $83
 
Total**** $61 $167 $228

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$61 $167 $228 $228 $228 $0
 
Total* $61 $167 $228 $228 $228 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2010 

04/01/2010 
10/06/2011 

08/25/2014 
10/01/2010 

04/30/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
05/01/2010 

05/31/2010 
08/25/2014 

08/25/2014 
08/01/2014 

09/01/2014 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 2

Bond Funding Cost
Adopted:
$61,180
Current Approved:
$126,183
Actual Expenditures:
$126,183

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31