6 Paratransit Replacement Buses

Description: Replace 6 diesel paratransit buses with 6 cleaner-burning, gasoline-powered paratransit buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Merced
City Merced
Zip Code 95340
 
Senate District
12
Assembly District 17
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  15      
Reduced Operating/Maintenance Cost        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
LARRY SHANKLAND (209) 385-7602 X4600   LSHANKLAND@CO.MERCED.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$89 $-13 $77
Non-bond Funding
Local**
$691 $-100 $591
 
Total**** $780 $-113 $667

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$780 $-113 $667 $667 $667 $0
 
Total* $780 $-113 $667 $667 $667 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2009 

07/01/2009 
 

 
07/01/2009 

07/01/2009 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2009 

10/01/2009 
 

 
06/30/2009 

06/30/2009 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 15
Reduced Operating/Maintenance Cost

Bond Funding Cost
Adopted:
$89,466
Current Approved:
$76,547
Actual Expenditures:
$76,547

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31