Caltrans Logo

SFMTA Light Rail Vehicle Rehabilitation

Description: Restore/Repair four damaged vehicles of LRV fleet and add new propulsion to the restored vehicles

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City San Francisco, Ca
Zip Code 94103
 
Senate District
03, 08
Assembly District 12, 13
Congressional District 08, 12
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      20  
Increased Ridership        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOEL C. GOLDBERG (415) 701-4499   JOEL.GOLDBERG@SFMTA.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$8,900 $0 $8,900
Non-bond Funding
State/Federal*
$3,104 $37,519 $40,622
Local**
$0 $20,471 $20,471
 
Total**** $12,004 $57,990 $69,994

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$12,004 $57,990 $69,994 $62,705 $62,705 $7,289
 
Total* $12,004 $57,990 $69,994 $62,705 $62,705 $7,289

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
04/08/2011 

04/08/2011 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

05/31/2009 
04/08/2011 

04/08/2011 
 

05/31/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2009 

03/31/2010 
01/15/2021 

01/15/2021 
10/29/2009 

06/30/2020 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2013 

01/31/2014 
01/15/2021 

01/15/2021 
07/01/2020 

12/31/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20
Increased Ridership

Bond Funding Cost
Adopted:
$8,900,000
Current Approved:
$8,900,000
Actual Expenditures:
$8,900,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31