Caltrans Logo

Traction Power Substation REPLACEMENT Program

Description: Replace the 14 traction power substations originally installed along the Guadalupe Light Rail Corridor 20 years ago

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Clara
City San Jose
Zip Code 95134
 
Senate District
23
Assembly District 13
Congressional District 16
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      74  
Reduced Operating/Maintenance Cost  20    19  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JEFFERY BALLOU (408) 321-5628   JEFFERY.BALLOU@VTA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $124 $124
PTMISEA-99314
$1,350 $119 $1,469
Non-bond Funding
State/Federal*
$4,050 $952 $5,002
 
Total**** $5,400 $1,194 $6,594

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$5,400 $1,194 $6,594 $6,594 $6,594 $0
 
Total* $5,400 $1,194 $6,594 $6,594 $6,594 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/21/2010 

02/28/2011 
03/06/2012 

08/23/2013 
04/01/2011 

02/01/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/26/2011 

02/25/2013 
02/24/2016 

02/24/2016 
09/01/2015 

06/30/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
02/26/2013 

05/20/2013 
03/08/2017 

02/23/2018 
07/28/2017 

12/31/2017 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 74
Reduced Operating/Maintenance Cost 20 19

Bond Funding Cost
Adopted:
$1,350,000
Current Approved:
$1,468,606
Actual Expenditures:
$1,468,606

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31