Traction Power Substation REHABILITATION

Description: Rehabilitate the existing traction power substations originally installed along Guadalupe Light Rail Corridor 20

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Clara
City San Jose
Zip Code 95134
 
Senate District
23
Assembly District 13
Congressional District 16
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  30      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JEFFERY BALLOU (408) 321-5628   JEFFERY.BALLOU@VTA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$1,150 $-119 $1,031
Non-bond Funding
State/Federal*
$3,450 $-457 $2,993
 
Total**** $4,600 $-576 $4,024

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$4,600 $-576 $4,024 $4,024 $4,024 $0
 
Total* $4,600 $-576 $4,024 $4,024 $4,024 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/2009 

11/12/2009 
03/06/2012 

03/06/2012 
10/15/2008 

05/18/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/24/2010 

10/26/2011 
03/06/2012 

02/26/2013 
03/25/2010 

12/31/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
10/27/2011 

01/23/2012 
02/26/2013 

02/26/2013 
12/31/2012 

03/01/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 30

Bond Funding Cost
Adopted:
$1,150,000
Current Approved:
$1,031,394
Actual Expenditures:
$1,031,394

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31