Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Traction Power Substation REHABILITATION |
Description: Rehabilitate the existing traction power substations originally installed along Guadalupe Light Rail Corridor 20
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Clara |
City | San Jose |
Zip Code | 95134 |
Senate District |
23 |
Assembly District | 13 |
Congressional District | 16 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 30 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
JEFFERY BALLOU | (408) 321-5628 | JEFFERY.BALLOU@VTA.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-99314 |
$1,150 | $-119 | $1,031 | ||||
Non-bond Funding | |||||||
State/Federal* |
$3,450 | $-457 | $2,993 | ||||
Total**** | $4,600 | $-576 | $4,024 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$4,600 | $-576 | $4,024 | $4,024 | $4,024 | $0 | |
Total* | $4,600 | $-576 | $4,024 | $4,024 | $4,024 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/30/2009 11/12/2009 |
03/06/2012 03/06/2012 |
10/15/2008 05/18/2009 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/24/2010 10/26/2011 |
03/06/2012 02/26/2013 |
03/25/2010 12/31/2012 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
10/27/2011 01/23/2012 |
02/26/2013 02/26/2013 |
12/31/2012 03/01/2013 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 30 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,150,000 |
Current Approved: |
$1,031,394 |
Actual Expenditures: |
$1,031,394 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31