Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Guadalupe Traction Power System |
Description: Rahabitation & replacement of contact wire, steady arms, section insulators, & under-bridge supports
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Clara |
City | San Jose |
Zip Code | 95134 |
Senate District |
23 |
Assembly District | 13 |
Congressional District | 16 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 75 | |
Reduced Operating/Maintenance Cost | 20 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
JEFFERY BALLOU | (408) 321-5628 | JEFFERY.BALLOU@VTA.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $81 | $81 | ||||
PTMISEA-99314 |
$1,150 | $0 | $1,150 | ||||
Non-bond Funding | |||||||
State/Federal* |
$3,450 | $323 | $3,773 | ||||
Total**** | $4,600 | $404 | $5,004 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$4,600 | $404 | $5,004 | $5,004 | $5,004 | $0 | |
Total* | $4,600 | $404 | $5,004 | $5,004 | $5,004 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/06/2010 07/22/2011 |
03/06/2012 09/09/2016 |
08/01/2011 06/30/2017 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
12/21/2011 12/20/2013 |
08/17/2012 02/17/2015 |
01/03/2013 09/01/2016 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
12/23/2013 03/18/2014 |
09/09/2016 09/09/2016 |
05/01/2018 05/31/2018 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 75 | |
Reduced Operating/Maintenance Cost | 20 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,150,000 |
Current Approved: |
$1,150,000 |
Actual Expenditures: |
$1,150,000 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31