Caltrans Logo

Purchase of Bus

Description: Purchase of one bus (25 passengers) to provide paratransit service for ADA qualified riders

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Siskiyou
City Yreka
Zip Code 96097
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  15    15  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
THOMAS L ANDERSON (530) 842-8295   tla2010@q.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$192 $-24 $168
PTMISEA-99314
$9 $0 $9
Non-bond Funding
 
Total**** $200 $-24 $176

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$200 $-24 $176 $176 $176 $0
 
Total* $200 $-24 $176 $176 $176 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/15/2009 

11/15/2009 
11/02/2011 

11/02/2011 
09/17/2010 

07/14/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
 

12/15/2009 
11/02/2011 

11/02/2011 
07/15/2011 

11/15/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 15 15

Bond Funding Cost
Adopted:
$200,109
Current Approved:
$176,116
Actual Expenditures:
$176,116

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31