Transit Bus Stop Facilities

Description: Planning, land purchase, design, engineering and construction of Transit Bus Stop Facilities with Administration Office

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Siskiyou
City Yreka, Ca
Zip Code 96097
 
Senate District
02
Assembly District 04
Congressional District 02
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    75  
Increased Ridership  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
BRIAN MCDERMOTT/MELISSA CUMMINS (530) 842-8295   MCUMMINS@CO.SISKIYOU.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$4 $26 $30
PTMISEA-99313
$1,527 $493 $2,021
PTMISEA-99314
$61 $22 $83
Non-bond Funding
State/Federal*
$166 $0 $166
Local**
$5 $644 $649
 
Total**** $1,764 $1,186 $2,950

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$5 $-5 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $438 $438 $-438
Right of Way
$363 $-2 $361 $0 $0 $361
Construction
$1,396 $1,193 $2,589 $2,512 $2,512 $77
 
Total* $1,764 $1,186 $2,950 $2,950 $2,950 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2012 

01/30/2012 
05/01/2014 

05/01/2014 
06/01/2013 

06/30/2013 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2012 

05/30/2012 
05/01/2014 

03/13/2015 
03/15/2014 

02/01/2015 
 

 


Begin Right of Way Phase

End Right of Way Phase
01/30/2012 

05/01/2012 
 

 
01/30/2012 

05/01/2012 
 

 


Begin Construction Phase

End Construction Phase
 

 
03/13/2015 

03/13/2015 
05/01/2015 

12/01/2015 
 

 


Begin Closeout Phase

End Closeout Phase
11/30/2013 

12/31/2013 
07/15/2016 

07/15/2016 
04/25/2016 

05/25/2016 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 75
Increased Ridership 15

Bond Funding Cost
Adopted:
$1,592,734
Current Approved:
$2,103,922
Actual Expenditures:
$2,103,922

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31