Bond Accountability
Facility Expansion, Operations & Maintenance |
Description: Design and construction of additional maintenance bays, bus wash for future use, and parking
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Tulare |
City | Visalia |
Zip Code | 93291 |
Senate District |
18 |
Assembly District | 34 |
Congressional District | 21 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 10 | 10 |
Reduced Operating/Maintenance Cost | 10 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
MONTY COX | (559) 713-4100 | TRANSIT@CI.VISALIA.CA.US |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $2 | $2 | ||||
PTMISEA-99313 |
$4,079 | $0 | $4,079 | ||||
PTMISEA-99314 |
$332 | $0 | $332 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,100 | $-226 | $874 | ||||
Local** |
$1,054 | $901 | $1,955 | ||||
Total**** | $6,564 | $676 | $7,240 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$272 | $0 | $272 | $272 | $272 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$6,292 | $676 | $6,968 | $2,879 | $2,879 | $4,089 | |
Total* | $6,564 | $676 | $7,240 | $3,151 | $3,151 | $4,089 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/01/2008 09/30/2009 |
|
12/01/2008 09/30/2009 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
06/01/2010 06/30/2011 |
08/26/2011 |
06/01/2010 09/30/2011 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
07/01/2011 07/31/2011 |
|
07/01/2011 07/31/2011 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 10 | 10 |
Reduced Operating/Maintenance Cost | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$4,410,545 |
Current Approved: |
$4,410,545 |
Actual Expenditures: |
$4,410,545 |
Click to view the Semi-Final Audit Report
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31