Transit Way Finding Implementation

Description: Develop and install transit-specific way finder signage

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Fresno
Zip Code 93706
 
Senate District
14, 16
Assembly District 31
Congressional District
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  3    3  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KATHLEEN HEALY (559) 621-1441   KATHLEEN.HEALY@FRESNO.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $99 $99
PTMISEA-99313
$1 $2 $2
PTMISEA-99314
$75 $0 $75
Non-bond Funding
 
Total**** $76 $100 $176

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$76 $100 $176 $177 $177 $-1
 
Total* $76 $100 $176 $177 $177 $-1

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/15/2010 

04/30/2011 
06/26/2014 

05/01/2015 
03/01/2013 

09/30/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/15/2011 

10/15/2011 
05/01/2015 

04/14/2016 
09/30/2015 

06/30/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
10/15/2011 

12/31/2011 
08/12/2019 

08/12/2019 
02/01/2018 

06/01/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 3 3

Bond Funding Cost
Adopted:
$75,575
Current Approved:
$77,387
Actual Expenditures:
$77,387

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31