Caltrans Logo

Purchase of 6 Diesel Buses

Description: Purchase 6 replacement diesel buese

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93301
 
Senate District
18
Assembly District 32
Congressional District 20, 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5      
Increased Ridership      15  
Reduced Operating/Maintenance Cost  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
BILLY ROBERTS (661) 862-5009   ROBERTSB@CO.KERN.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$666 $-16 $650
PTMISEA-99314
$34 $-34 $0
Non-bond Funding
 
Total**** $700 $-50 $650

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$700 $-50 $650 $650 $650 $0
 
Total* $700 $-50 $650 $650 $650 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
08/26/2011 

08/26/2011 
03/31/2009 

03/31/2009 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
08/26/2011 

08/26/2011 
03/31/2009 

08/18/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2010 

07/01/2010 
08/26/2011 

08/26/2011 
01/30/2012 

06/30/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
09/30/2011 

12/31/2011 
08/26/2012 

06/26/2013 
07/30/2012 

05/30/2013 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5
Increased Ridership 15
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$700,343
Current Approved:
$650,230
Actual Expenditures:
$650,230

Click to view the Semi-Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31