Intermodal Aerial Station

Description: Construction of an aerial light rail station as the terminus of the Phase I Expo light rail extension.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Culver City
Zip Code 90232
 
Senate District
26
Assembly District 47
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  15    15  
Reduced Emissions  15    15  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JANE LEONARD (310) 253-6523   JANE.LEONARD@CULVERCITY.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$100 $0 $100
Non-bond Funding
State/Federal*
$2,226 $-251 $1,975
Local**
$1,674 $251 $1,925
 
Total**** $4,000 $0 $4,000

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$4,000 $0 $4,000 $100 $100 $3,900
 
Total* $4,000 $0 $4,000 $100 $100 $3,900

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/1999 

02/01/2006 
 

 
06/01/1999 

02/01/2006 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2003 

07/01/2009 
03/08/2012 

03/08/2012 
01/01/2008 

05/01/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2009 

12/01/2010 
 

02/22/2013 
07/01/2009 

06/01/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2011 

06/01/2012 
02/22/2013 

02/22/2013 
06/01/2012 

12/31/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 15 15
Reduced Emissions 15 15

Bond Funding Cost
Adopted:
$100,000
Current Approved:
$100,000
Actual Expenditures:
$100,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31