Caltrain Station Improvements

Description: Platform, Station, Track, and Signal Work

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Clara
City San Carlos, Ca
Zip Code 94070
 
Senate District
11
Assembly District 12, 19, 21
Congressional District 12, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
PETER SKINNER (650) 622-7818   SKINNERP@SAMTRANS.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99314
$841 $0 $841
Non-bond Funding
State/Federal*
$8,646 $-0 $8,646
Local**
$16,510 $-1,037 $15,474
 
Total**** $25,998 $-1,036 $24,962

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $2,164 $2,164 $-2,164
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$25,998 $-1,036 $24,962 $22,798 $22,798 $2,164
 
Total* $25,998 $-1,036 $24,962 $24,962 $24,962 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2005 

11/30/2008 
 

 
12/01/2005 

11/30/2008 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2005 

04/01/2009 
 

 
12/01/2005 

04/01/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
12/01/2005 

04/30/2009 
 

 
12/01/2005 

04/30/2009 
100   

 


Begin Construction Phase

End Construction Phase
12/01/2009 

12/31/2011 
08/28/2013 

08/28/2013 
01/19/2009 

08/31/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2012 

01/31/2012 
02/21/2013 

08/28/2013 
09/01/2012 

05/31/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5 5

Bond Funding Cost
Adopted:
$841,308
Current Approved:
$841,308
Actual Expenditures:
$841,308

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31