Caltrans Logo

Driver and Vehicle Safety Enhancements

Description: Installation of outdoor safety and security lighting and video camera at the transit office and vehicle storage yard

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Luis Obispo
City Atascadero
Zip Code 93422
 
Senate District
15
Assembly District 33
Congressional District
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20    20  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
VALERIE HUMPHREY (805) 470-3486   VHUMPHREY@ATASCADERO.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99314
$9 $0 $9
Non-bond Funding
State/Federal*
$19 $0 $19
 
Total**** $28 $0 $28

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $-0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$28 $0 $28 $9 $9 $20
 
Total* $28 $0 $28 $9 $9 $19

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/01/2010 

12/31/2010 
08/29/2012 

10/28/2011 
11/01/2011 

03/31/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2011 

02/01/2011 
08/29/2012 

08/29/2012 
03/31/2012 

05/10/2012 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20 20

Bond Funding Cost
Adopted:
$8,759
Current Approved:
$8,759
Actual Expenditures:
$8,759

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31