Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Santa Maria Area Transit Bus Purchase |
Description: Purchase of 3 40', low floor Gillig buses.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Barbara |
City | Santa Barbara |
Zip Code | 93110 |
Senate District |
15, 19 |
Assembly District | 33 |
Congressional District | |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 80 | 80 |
Reduced Emissions | 100 | 100 |
Reduced Operating/Maintenance Cost | 80 | 80 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
Stephen VanDenburgh | (805) 961-8900 | svandenburgh@sbcag.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $0 | $0 | ||||
PTMISEA-99313 |
$17 | $0 | $17 | ||||
PTMISEA-99314 |
$8 | $0 | $8 | ||||
Non-bond Funding | |||||||
State/Federal* |
$975 | $0 | $975 | ||||
Local** |
$41 | $0 | $41 | ||||
Total**** | $1,041 | $0 | $1,041 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,041 | $0 | $1,041 | $25 | $25 | $1,016 | |
Total* | $1,041 | $0 | $1,041 | $25 | $25 | $1,016 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/01/2011 11/01/2012 |
09/16/2014 09/16/2014 |
08/01/2012 03/21/2014 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
|
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 80 | 80 |
Reduced Emissions | 100 | 100 |
Reduced Operating/Maintenance Cost | 80 | 80 |
Bond Funding Cost | |
---|---|
Adopted: |
$108,473 |
Current Approved: |
$25,150 |
Actual Expenditures: |
$25,150 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31