Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
SYVT - Transit Stop Upgrades |
Description: Upgrades to transit stops throughout the SYVT service area
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Barbara |
City | Solvang |
Zip Code | 93463 |
Senate District |
19 |
Assembly District | 35 |
Congressional District | |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 3 | 3 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
DANA WHITE | (805) 688-5575 | DANAW@CITYOFSOLVANG.COM |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $1 | $1 | ||||
PTMISEA-99313 |
$239 | $-56 | $183 | ||||
PTMISEA-99314 |
$7 | $-4 | $2 | ||||
Non-bond Funding | |||||||
Local** |
$35 | $0 | $35 | ||||
Total**** | $281 | $-59 | $222 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$10 | $0 | $10 | $0 | $0 | $10 | |
Design(PS&E) |
$25 | $0 | $25 | $30 | $30 | $-5 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$246 | $-59 | $187 | $157 | $157 | $30 | |
Total* | $281 | $-59 | $222 | $187 | $187 | $35 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/01/2010 11/01/2010 |
09/13/2011 09/13/2011 |
10/01/2011 12/01/2011 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
03/01/2011 03/31/2011 |
12/12/2012 08/29/2012 |
03/01/2012 08/01/2012 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
02/01/2011 02/28/2011 |
08/29/2012 12/12/2012 |
07/01/2012 09/01/2012 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 3 | 3 |
Bond Funding Cost | |
---|---|
Adopted: |
$245,848 |
Current Approved: |
$185,619 |
Actual Expenditures: |
$185,619 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31