Transit Related Equipment

Description: Purchase 2-way radio upgrade

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Siskiyou
City Yreka, Ca
Zip Code 96097
 
Senate District
02
Assembly District 04
Congressional District 02
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability        
Reduced Operating/Maintenance Cost  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
THOMAS L. ANDERSON (530) 842-8295   tla2010@q.com
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$181 $-141 $40
PTMISEA-99314
$8 $0 $8
Non-bond Funding
 
Total**** $189 $-141 $48

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$189 $-141 $48 $48 $48 $0
 
Total* $189 $-141 $48 $48 $48 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/15/2010 

12/15/2010 
11/03/2011 

11/03/2011 
06/16/2011 

08/26/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
01/03/2011 

02/15/2011 
09/01/2011 

09/01/2011 
08/31/2011 

11/15/2011 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
$189,134
Current Approved:
$47,635
Actual Expenditures:
$47,635

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31