Simi Valley Transit - CNG Fueling Facility Modernization

Description: Install two fast-fill fueling stations, six high-pressure fuel dispensing storage vessels & upgrades 26 CNG slow-fill dispensers and accesories.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Ventura
City Ventura
Zip Code 93003
 
Senate District
19
Assembly District 37
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  50      
Reduced Emissions  25      
Reduced Operating/Maintenance Cost  25      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
PETER DEHAAN (805) 642-1591 X106   PDEHAAN@GOVENTURA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $29 $29
PTMISEA-99313
$1,267 $-720 $547
Non-bond Funding
State/Federal*
$0 $1,400 $1,400
 
Total**** $1,267 $708 $1,975

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$200 $-163 $37 $132 $132 $-96
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,067 $872 $1,939 $235 $235 $1,703
 
Total* $1,267 $708 $1,975 $368 $368 $1,608

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/21/2010 

08/09/2010 
03/17/2015 

03/17/2015 
04/20/2015 

09/28/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
09/06/2010 

09/13/2010 
03/17/2015 

03/17/2015 
10/14/2013 

10/30/2013 
100   

 


Begin Construction Phase

End Construction Phase
10/11/2010 

11/15/2010 
04/07/2023 

04/20/2023 
10/22/2021 

04/15/2023 
95   

 


Begin Closeout Phase

End Closeout Phase
12/13/2010 

12/30/2010 
04/20/2023 

04/20/2023 
04/15/2023 

05/15/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50
Reduced Emissions 25
Reduced Operating/Maintenance Cost 25

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31