Simi Valley Transit - CNG Fueling Facility Modernization

Description: Install two fast-fill fueling stations, six high-pressure fuel dispensing storage vessels & upgrades 26 CNG slow-fill dispensers and accesories.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Ventura
City Ventura
Zip Code 93003
 
Senate District
19
Assembly District 37
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  50      
Reduced Emissions  25      
Reduced Operating/Maintenance Cost  25      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
PETER DEHAAN (805) 642-1591 X106   PDEHAAN@GOVENTURA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $34 $34
PTMISEA-99313
$1,267 $-720 $547
Non-bond Funding
State/Federal*
$0 $1,400 $1,400
 
Total**** $1,267 $714 $1,981

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$200 $-163 $37 $131 $131 $-95
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,067 $877 $1,944 $415 $415 $1,529
 
Total* $1,267 $714 $1,981 $547 $547 $1,434

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/21/2010 

08/09/2010 
03/17/2015 

03/17/2015 
03/21/2010 

09/28/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
09/06/2010 

09/13/2010 
03/17/2015 

03/17/2015 
10/14/2013 

10/30/2013 
100   

 


Begin Construction Phase

End Construction Phase
10/11/2010 

11/15/2010 
09/11/2024 

09/11/2024 
04/30/2012 

12/16/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
12/13/2010 

12/30/2010 
09/11/2024 

09/11/2024 
02/28/2023 

12/16/2023 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50
Reduced Emissions 25
Reduced Operating/Maintenance Cost 25

Bond Funding Cost
Adopted:
$1,267,149
Current Approved:
$546,764
Actual Expenditures:
$546,764

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31