Plumas County Bus Yard

Description: Construction of a bus parking area within the Plumas County Maintenance Yard in Quincy

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Plumas
City Quincy
Zip Code 95971
 
Senate District
03
Assembly District 01
Congressional District 04
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  100    33  
Reduced Operating/Maintenance Cost  10    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOHN MANNLE (530) 283-6498   JOHNMANNLE@COUNTYOFPLUMAS.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
LSR
$0 $86 $86
PTMISEA-Interest
$0 $42 $42
PTMISEA-99313
$319 $92 $411
Non-bond Funding
Local**
$0 $8 $8
 
Total**** $319 $228 $547

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $8 $8 $8 $8 $0
Design(PS&E)
$75 $-75 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$244 $294 $538 $538 $538 $0
 
Total* $319 $228 $547 $547 $547 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
09/12/2012 

09/12/2012 
11/01/2011 

08/01/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2012 

05/01/2013 
10/19/2011 

09/21/2016 
09/01/2012 

04/06/2016 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2013 

10/01/2013 
09/21/2016 

09/05/2023 
04/07/2016 

06/30/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
11/01/2013 

01/01/2014 
09/05/2023 

02/15/2023 
06/01/2023 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 100 33
Reduced Operating/Maintenance Cost 10 5

Bond Funding Cost
Adopted:
$318,930
Current Approved:
$410,660
Actual Expenditures:
$410,660

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31