                            Description: Project is to upgrade facilities at bus intermodal zone at Richmond BART station
                             | 
                    
- Project Information
 - Contacts
 - Cost by Fund Source
 - Cost by Component
 - Schedule
 - Map
 - Closeout Info
 
| Project Location | |
|---|---|
| County | 
                                    Contra Costa | 
| City | Oakland | 
| Zip Code | 94604 | 
| Senate District | 
                                    14 | 
                                
| Assembly District | 09 | 
| Congressional District | 07 | 
| Caltrans District | 
                                    04 | 
                                
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increased Ridership | 3 | |
| Reduced Operating/Maintenance Cost | 5 | 3 | 
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA | 
                                    
                                    
                                        
                                            MICHAEL TANNER | (510) 464-6433 | MTANNER@BART.GOV | 
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a  | 
                                    Approved Changes (06/30/2025 b=c-a  | 
                                    Current Approved (06/30/2025 c  | 
                                |||||
| Bond Funding | |||||||
| PTMISEA-99313 | 
                                            $745 | $0 | $745 | ||||
| Non-bond Funding | |||||||
| State/Federal* | 
                                            $0 | $2,900 | $2,900 | ||||
| Local** | 
                                            $186 | $500 | $686 | ||||
| Total**** | $931 | $3,400 | $4,331 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a  | 
                                    Approved Changes (06/30/2025 b=c-a  | 
                                    Current Approved (06/30/2025 c  | 
                                    Cost to Date** (06/30/2025 d  | 
                                    
                                        
                                            Cost Forecast (06/30/2025 e  | 
                                            Cost Variance f=c-e  | 
                                        
                                    
                                ||
| Environmental | 
                                        $0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) | 
                                        $153 | $354 | $507 | $507 | $507 | $0 | |
| Right of Way | 
                                    $0 | $0 | $0 | $0 | $0 | $0 | |
| Construction | 
                                    $778 | $3,046 | $3,824 | $3,824 | $3,824 | $0 | |
| Total* | $931 | $3,400 | $4,331 | $4,331 | $4,331 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a  | 
                                    Approved Changes (mm/dd/yyyy) b  | 
                                    Current Approved (06/30/2025) c  | 
                                    % Complete (06/30/2025) d  | 
                                    Schedule Forecast (06/30/2025) e  | 
                                    Schedule Variance (months) f=c-e  | 
                                
| 
                                        
                                            Begin Environmental Phase
                                             End Environmental Phase  | 
                                      | 
                                      | 
                                      | 
                                    0 |   | 
                                    0  0  | 
                                
| 
                                        Begin Design (PS&E) Phase
                                         End Design (PS&E) Phase  | 
                                    03/01/2009  01/01/2010  | 
                                    06/24/2019  06/24/2019  | 
                                    06/01/2013  09/01/2014  | 
                                    100 |   | 
                                    0  0  | 
                                
| 
                                        Begin Right of Way Phase
                                         End Right of Way Phase  | 
                                      | 
                                      | 
                                      | 
                                    0 |   | 
                                    0  0  | 
                                
| 
                                        Begin Construction Phase
                                         End Construction Phase  | 
                                    03/01/2010  03/01/2011  | 
                                    06/24/2019  06/24/2019  | 
                                    03/01/2015  10/01/2018  | 
                                    100 |   | 
                                    0  0  | 
                                
| 
                                        Begin Closeout Phase
                                         End Closeout Phase  | 
                                    04/01/2001  06/01/2011  | 
                                    06/24/2019  06/24/2019  | 
                                    08/01/2019  12/01/2019  | 
                                    0 |   | 
                                    0  0  | 
                                
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual | 
| Increased Ridership | 3 | |
| Reduced Operating/Maintenance Cost | 5 | 3 | 
| Bond Funding Cost | |
|---|---|
| Adopted: | 
                                    $744,800 | 
| Current Approved: | 
                                    $744,800 | 
| Actual Expenditures: | 
                                    $744,800 | 
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31