Imperial Valley College Bus Transfer Terminal (Phase II) |
|
Description: Phase II of the Imperial Valley College Bus Transfer Terminal
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Imperial |
| City | El Centro |
| Zip Code | 92243 |
| Senate District |
40 |
| Assembly District | 80 |
| Congressional District | 51 |
| Caltrans District |
11 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 2 | 2 |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
KATHI WILLIAMS | (760) 482-4290 | KATHIWILLIAM@CO.IMPERIAL.CA.US |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $59 | $59 | ||||
| PTMISEA-99313 |
$900 | $21 | $920 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$133 | $0 | $133 | ||||
| Local** |
$377 | $-377 | $0 | ||||
| Total**** | $1,410 | $-297 | $1,112 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$185 | $-169 | $16 | $16 | $16 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$1,225 | $-129 | $1,096 | $1,096 | $1,096 | $0 | |
| Total* | $1,410 | $-297 | $1,112 | $1,112 | $1,112 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
03/01/2008 04/01/2008 |
|
03/01/2008 04/01/2008 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2009 05/01/2009 |
08/26/2011 |
01/01/2009 09/30/2011 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
06/01/2009 11/01/2009 |
08/26/2011 08/26/2011 |
07/31/2011 04/30/2012 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
01/01/2010 02/01/2010 |
09/04/2012 09/04/2012 |
08/01/2012 09/01/2012 |
0 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 2 | 2 |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$899,616 |
| Current Approved: |
$920,161 |
| Actual Expenditures: |
$920,161 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31