Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
City of Vallejo Purchase 1 Hybrid Bus |
|
Description: Funding is to replace 1 fully depreciated bus (a part of the Vallejo 20 bus fleet replacement plan)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Solano |
| City | Vallejo |
| Zip Code | 94590 |
| Senate District |
02 |
| Assembly District | 11 |
| Congressional District | 08 |
| Caltrans District |
04 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Reduced Emissions | ||
| Reduced Operating/Maintenance Cost | ||
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
CRYSTAL ODUM FORD | (707) 428-5741 | CODUMFORD@CI.VALLEJO.CA.US |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99313 |
$0 | $294 | $294 | ||||
| PTMISEA-99314 |
$532 | $-532 | $0 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$0 | $4,112 | $4,112 | ||||
| Total**** | $532 | $3,874 | $4,406 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$532 | $3,874 | $4,406 | $4,406 | $4,406 | $0 | |
| Total* | $532 | $3,874 | $4,406 | $4,406 | $4,406 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
04/07/2009 05/07/2009 |
11/16/2011 11/16/2011 |
11/13/2009 05/15/2011 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
01/01/2011 04/30/2011 |
|
01/01/2011 04/30/2011 |
0 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Reduced Emissions | ||
| Reduced Operating/Maintenance Cost | ||
| Bond Funding Cost | |
|---|---|
| Adopted: |
$531,829 |
| Current Approved: |
$293,914 |
| Actual Expenditures: |
$293,914 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31
