La Sierra Station Parking Lot Expansion |
|
Description: Expanded parking to add approximately 500 spaces
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Riverside |
| City | Riverside |
| Zip Code | 92501 |
| Senate District |
31 |
| Assembly District | 66 |
| Congressional District | |
| Caltrans District |
08 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 1 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
SHELDON PETERSON | (951) 787-7928 | SPETERSON@RCTC.ORG |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99313 |
$871 | $-803 | $68 | ||||
| Non-bond Funding | |||||||
| Local** |
$1,587 | $-1,587 | $0 | ||||
| Total**** | $2,458 | $-2,390 | $68 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$100 | $-32 | $68 | $68 | $68 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$2,358 | $-2,358 | $0 | $0 | $0 | $0 | |
| Total* | $2,458 | $-2,390 | $68 | $68 | $68 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
03/01/2009 04/01/2009 |
|
03/01/2009 04/01/2009 |
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/2009 09/01/2009 |
03/22/2011 |
04/01/2009 04/01/2011 |
90 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
10/01/2009 04/01/2010 |
09/10/2012 09/10/2012 |
11/30/2011 11/30/2011 |
0 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
04/01/2010 05/01/2010 |
09/10/2012 09/10/2012 |
11/30/2011 11/30/2011 |
0 | |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 1 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$870,637 |
| Current Approved: |
$67,780 |
| Actual Expenditures: |
$67,780 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31