Caltrans Logo

CNG Station Repairs & Design

Description: Repairs to the City's CNG station as well as design work for the replacement

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Banning
Zip Code 92220
 
Senate District
23
Assembly District 42
Congressional District 36
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  50    50  
Reduced Operating/Maintenance Cost  30    30  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ARTURO VELA (951) 922-3130   AVELA@BANNINGCA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $6 $6
PTMISEA-99313
$58 $0 $58
PTMISEA-99314
$11 $0 $11
Non-bond Funding
 
Total**** $70 $6 $76

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$70 $6 $76 $76 $76 $0
 
Total* $70 $6 $76 $76 $76 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/13/2017 

07/01/2018 
 

 
02/13/2017 

07/01/2018 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2018 

01/31/2019 
 

 
07/01/2018 

01/31/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
02/01/2019 

06/30/2020 
 

06/01/2020 
02/01/2019 

06/01/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50 50
Reduced Operating/Maintenance Cost 30 30

Bond Funding Cost
Adopted:
$69,542
Current Approved:
$69,542
Actual Expenditures:
$69,542

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31