Transit Transfer Center

Description: The acquisition of property and construction of the transit center.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Turlock
Zip Code 95380
 
Senate District
12
Assembly District 25
Congressional District 19
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ROGER FALL (209) 668-5520   RFALL@TURLOCK.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$1,253 $281 $1,534
PTMISEA-99314
$15 $0 $15
Non-bond Funding
State/Federal*
$0 $3,893 $3,893
 
Total**** $1,268 $4,174 $5,442

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,268 $4,174 $5,442 $5,442 $5,442 $0
 
Total* $1,268 $4,174 $5,442 $5,442 $5,442 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/02/2009 

06/15/2009 
 

 
06/02/2009 

06/15/2009 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/15/2009 

02/01/2010 
03/09/2011 

10/25/2013 
02/01/2010 

04/01/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
07/15/2009 

11/01/2009 
03/09/2011 

02/21/2013 
08/01/2010 

03/12/2013 
100   

 


Begin Construction Phase

End Construction Phase
05/01/2010 

07/01/2010 
09/29/2011 

10/25/2013 
07/28/2011 

12/31/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
08/01/2010 

09/01/2010 
10/25/2013 

10/25/2013 
09/01/2013 

10/01/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10

Bond Funding Cost
Adopted:
$1,267,848
Current Approved:
$1,549,015
Actual Expenditures:
$1,549,015

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31