Description: Bus Facilities and Maintenance Equipment
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
San Joaquin |
| City | Stockton |
| Zip Code | 95202 |
| Senate District |
05, 14 |
| Assembly District | 15, 17, 26 |
| Congressional District | |
| Caltrans District |
10 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 5 | |
| Reduced Operating/Maintenance Cost | 1 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
DONNA DEMARTINO | (209) 948-5566 X613 | DDEMARTINO@SANJOAQUINRTD.COM |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-99314 |
$127 | $-36 | $91 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$509 | $719 | $1,228 | ||||
| Total**** | $636 | $683 | $1,319 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$636 | $683 | $1,319 | $1,319 | $1,319 | $0 | |
| Total* | $636 | $683 | $1,319 | $1,319 | $1,319 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
07/31/2009 06/30/2011 |
08/26/2011 09/11/2012 |
07/31/2011 06/30/2013 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
06/30/2011 07/31/2011 |
10/21/2016 10/21/2016 |
09/01/2016 09/30/2016 |
0 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 5 | |
| Reduced Operating/Maintenance Cost | 1 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$127,163 |
| Current Approved: |
$91,361 |
| Actual Expenditures: |
$91,361 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31