TO Transit - Transit Center Expansion |
|
Description: Expand parking by 60-78 spaces at the intermodal transportation hub in Thousand Oaks.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Ventura |
| City | Ventura |
| Zip Code | 93003 |
| Senate District |
19 |
| Assembly District | 37 |
| Congressional District | |
| Caltrans District |
07 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 10 | 5 |
| Reduced Operating/Maintenance Cost | 20 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
PETER DEHAAN | (805) 642-1591 X106 | PDEHAAN@GOVENTURA.ORG |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $31 | $31 | ||||
| PTMISEA-99313 |
$1,250 | $0 | $1,250 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$0 | $185 | $185 | ||||
| Local** |
$125 | $-79 | $46 | ||||
| Total**** | $1,375 | $137 | $1,512 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$125 | $-65 | $60 | $0 | $0 | $60 | |
| Design(PS&E) |
$200 | $0 | $200 | $0 | $0 | $200 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$1,050 | $202 | $1,252 | $1,281 | $1,281 | $-29 | |
| Total* | $1,375 | $137 | $1,512 | $1,281 | $1,281 | $231 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/2010 04/01/2011 |
03/15/2012 |
07/01/2010 02/01/2011 |
100 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2010 04/01/2011 |
04/11/2013 03/15/2012 |
02/01/2011 03/01/2012 |
100 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
08/30/2011 05/30/2012 |
04/11/2013 09/13/2013 |
01/22/2013 08/30/2013 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
07/01/2012 10/30/2012 |
09/13/2013 11/16/2015 |
09/01/2013 07/31/2015 |
0 | |
0 0 |
????????
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increased Ridership | 10 | 5 |
| Reduced Operating/Maintenance Cost | 20 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$1,250,000 |
| Current Approved: |
$1,250,000 |
| Actual Expenditures: |
$1,250,000 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31