Install Ramp Metering Stations and Widen On-ramps |
Description: In San Bernardino County, from Route 15 to Route 215. Install ramp metering. (Prop 1B Bond Funded Project)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | Colton |
Zip Code | 92324 |
Senate District |
32 |
Assembly District | 62 |
Congressional District | 42 |
Caltrans District |
08 |
County/State Route | San Bernardino 10 |
Postmile Begin/End | 9.9 R 24.5 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 11 | 11 |
Ramp Widenings | 12 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Meardey Tim | (909) 383-6480 | meardey_tim@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Meardey Tim | (909) 383-6480 | meardey_tim@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Meardey Tim | (909) 383-6480 | meardey_tim@dot.ca.gov | |
Construction Phase |
Department of Transportation | Meardey Tim | (909) 383-6480 | meardey_tim@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Meardey Tim | (909) 383-6480 | meardey_tim@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$24,384 | $-9,440 | $14,944 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $134 | $134 | ||||
Total**** | $24,384 | $-9,306 | $15,078 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,500 | $0 | $1,500 | $443 | |||
Design(PS&E) |
$1,700 | $0 | $1,700 | $2,323 | |||
Right of Way |
$184 | $0 | $184 | $5 | |||
Construction |
$21,000 | $-9,306 | $11,694 | $10,447 | |||
Total* | $24,384 | $-9,306 | $15,078 | $13,217 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/2007 07/01/2008 |
|
07/01/2007 07/01/2008 |
100 | 07/02/2007 07/01/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2008 01/01/2010 |
|
07/01/2008 01/01/2010 |
100 | 07/01/2008 04/19/2011 |
0 -16 |
Begin Right of Way Phase
End Right of Way Phase |
07/01/2008 05/01/2010 |
|
07/01/2008 05/01/2010 |
100 | 07/01/2008 12/29/2010 |
0 -8 |
Begin Construction Phase
End Construction Phase |
10/01/2010 10/01/2012 |
|
10/01/2010 10/01/2012 |
100 | 04/13/2012 12/15/2014 |
-19 -27 |
Begin Closeout Phase
End Closeout Phase |
11/01/2012 11/01/2013 |
|
11/01/2012 11/01/2013 |
25 | 12/15/2014 12/15/2015 |
-26 -26 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 11 | 11 |
Ramp Widenings | 12 |
Bond Funding Cost | |
---|---|
Adopted: |
$24,384,000 |
Current Approved: |
$24,384,000 |
Actual Expenditures: |
$13,326,000 |
Status as of December 31, 2023.