Install Ramp Metering Stations and Widen On-ramps

Description: In San Bernardino County, from Route 15 to Route 215. Install ramp metering. (Prop 1B Bond Funded Project)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Colton
Zip Code 92324
 
Senate District
32
Assembly District 62
Congressional District 42
 
Caltrans District
08
 
 
County/State Route San Bernardino 10
Postmile Begin/End 9.9 R  24.5
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  11    11  
Ramp Widenings  12      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Meardey Tim (909) 383-6480   meardey_tim@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Meardey Tim (909) 383-6480   meardey_tim@dot.ca.gov
Right of Way Phase
Department of Transportation Meardey Tim (909) 383-6480   meardey_tim@dot.ca.gov
Construction Phase
Department of Transportation Meardey Tim (909) 383-6480   meardey_tim@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Meardey Tim (909) 383-6480   meardey_tim@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$24,384 $-9,440 $14,944
Non-bond Funding
State/Federal*
$0 $134 $134
 
Total**** $24,384 $-9,306 $15,078

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,500 $0 $1,500 $443
Design(PS&E)
$1,700 $0 $1,700 $2,323
Right of Way
$184 $0 $184 $5
Construction
$21,000 $-9,306 $11,694 $10,447
 
Total* $24,384 $-9,306 $15,078 $13,217

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

07/01/2008 
 

 
07/01/2007 

07/01/2008 
100  07/02/2007 

07/01/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2008 

01/01/2010 
 

 
07/01/2008 

01/01/2010 
100  07/01/2008 

04/19/2011 


-16 
Begin Right of Way Phase

End Right of Way Phase
07/01/2008 

05/01/2010 
 

 
07/01/2008 

05/01/2010 
100  07/01/2008 

12/29/2010 


-8 
Begin Construction Phase

End Construction Phase
10/01/2010 

10/01/2012 
 

 
10/01/2010 

10/01/2012 
100  04/13/2012 

12/15/2014 
-19 

-27 
Begin Closeout Phase

End Closeout Phase
11/01/2012 

11/01/2013 
 

 
11/01/2012 

11/01/2013 
25  12/15/2014 

12/15/2015 
-26 

-26 
????????
Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 11 11
Ramp Widenings 12

Bond Funding Cost
Adopted:
$24,384,000
Current Approved:
$24,384,000
Actual Expenditures:
$13,326,000

 

Status as of December 31, 2023.