Wheaton Springs - vehicle enforcement facility.

Description: Near Wheaton Springs, from 1.2 miles north of Nipton Road to 0.5 miles south of Yates Well Road. Construct commercial vehicle enforcement facility.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Nipton
Zip Code 92364
 
Senate District
18
Assembly District 34
Congressional District 41
 
Caltrans District
08
 
 
County/State Route San Bernardino 15
Postmile Begin/End 177.3 181.1
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Jason Bennecke 909-556-8852   jason_bennecke@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Jason Bennecke 909-556-8852   jason_bennecke@dot.ca.gov
Right of Way Phase
Department of Transportation Jason Bennecke 909-556-8852   jason_bennecke@dot.ca.gov
Construction Phase
Department of Transportation Jason Bennecke 909-556-8852   jason_bennecke@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Jason Bennecke 909-556-8852   jason_bennecke@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$65,743 $-38,946 $26,797
Non-bond Funding
State/Federal*
$0 $35,510 $35,510
Local**
$0 $0 $0
 
Total**** $65,743 $-3,436 $62,307

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,385 $0 $1,385 $1,531
Design(PS&E)
$13,000 $0 $13,000 $19,971
Right of Way
$2,031 $0 $2,031 $1,217
Construction
$49,327 $-3,436 $45,891 $53,288
 
Total* $65,743 $-3,436 $62,307 $76,007

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
04/01/1999 

03/31/2006 
100  04/01/1999 

03/31/2006 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

04/07/2010 
100   

04/07/2010 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/29/2013 

09/15/2014 
 

 
11/01/2013 

03/15/2017 
11/01/2013 

12/15/2015 


15 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

06/03/2019 
 

07/01/2022 


-37 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.