Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Install Vehicle Detection Stations (VDS) |
Description: In Riverside and San Bernardino Counties on Routes 10, 91 and 215 (portion also in Los Angeles County on Route 5). Install Vehicle Detection Systems (VDS). (Prop 1B Bond Funded Project)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside |
City | Riverside, San Bernardino |
Zip Code | 92503, 92506 |
Senate District |
22, 24, 26 |
Assembly District | 47, 48, 49, 57, 61 |
Congressional District | 26 |
Caltrans District |
08 |
County/State Route | Riverside 10 |
Postmile Begin/End | 0.2 6.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 342 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Meardey Tim | (909) 383-6480 | Meardey_tim@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Meardey Tim | (909) 383-6480 | Meardey_tim@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Meardey Tim | (909) 383-6480 | Meardey_tim@dot.ca.gov | |
Construction Phase |
Department of Transportation | Meardey Tim | (909) 383-6480 | Meardey_tim@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Meardey Tim | (909) 383-6480 | Meardey_tim@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$6,760 | $-293 | $6,467 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Total**** | $6,760 | $-293 | $6,467 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$300 | $0 | $300 | $23 | |||
Design(PS&E) |
$570 | $0 | $570 | $317 | |||
Right of Way |
$50 | $0 | $50 | $0 | |||
Construction |
$5,840 | $-293 | $5,547 | $3,832 | |||
Total* | $6,760 | $-293 | $6,467 | $4,173 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/01/2007 08/01/2007 |
|
06/01/2007 08/01/2007 |
100 | 06/22/2007 08/02/2007 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2007 11/01/2007 |
|
07/01/2007 11/01/2007 |
100 | 01/31/2008 |
0 -3 |
Begin Right of Way Phase
End Right of Way Phase |
09/01/2007 12/01/2007 |
|
09/01/2007 12/01/2007 |
100 | 09/18/2007 11/14/2007 |
-1 1 |
Begin Construction Phase
End Construction Phase |
06/01/2008 12/01/2008 |
|
06/01/2008 12/01/2008 |
100 | 10/04/2008 04/01/2009 |
-4 -4 |
Begin Closeout Phase
End Closeout Phase |
12/01/2008 03/01/2009 |
|
12/01/2008 03/01/2009 |
100 | 04/01/2010 |
0 -13 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 342 |
Bond Funding Cost | |
---|---|
Adopted: |
$6,760,000 |
Current Approved: |
$6,760,000 |
Actual Expenditures: |
$4,204,616 |
Status as of December 31, 2023.