FCRTA's Rolling Stock Replacement Cut-Away Vans

Description: 10 Replacement Cut-Away Vans

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Fresno
Zip Code 93721
 
Senate District
14, 16
Assembly District 29, 30, 31
Congressional District 18, 19, 20, 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  10    10  
Reduced Emissions  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JEFFREY D. WEBSTER (559) 233-6789   JWEBSTER_RURALTRANSIT@FRESNOCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$938 $0 $938
PTMISEA-99314
$24 $0 $24
Non-bond Funding
Local**
$0 $0 $0
 
Total**** $963 $0 $963

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$963 $0 $963 $1,231 $1,231 $-268
 
Total* $963 $0 $963 $1,231 $1,231 $-268

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/26/2008 

01/29/2009 
03/29/2011 

03/29/2011 
06/26/2008 

03/16/2009 
 

 


Begin Closeout Phase

End Closeout Phase
01/30/2009 

02/28/2009 
03/29/2011 

03/29/2011 
07/30/2009 

11/30/2009 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 10 10
Reduced Emissions 10 10

Bond Funding Cost
Adopted:
$962,733
Current Approved:
$962,733
Actual Expenditures:
$962,733

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31