Caltrans Logo

GPS Tracking System

Description: Installation of GPS tracking system on all regional transit buses & purchase of necessary infrastructure

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Humboldt
City Eureka
Zip Code 95501
 
Senate District
02
Assembly District 01
Congressional District 01
 
Caltrans District
01
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10      
Reduced Emissions      30  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GREG PRATT (707) 443-0826   GREG PRATT
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $24 $24
PTMISEA-99313
$398 $0 $398
PTMISEA-99314
$64 $0 $64
Non-bond Funding
 
Total**** $462 $24 $486

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$462 $24 $486 $486 $486 $0
 
Total* $462 $24 $486 $486 $486 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2009 

06/01/2009 
 

 
01/01/2011 

09/30/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
11/25/2013 

11/25/2013 
08/31/2012 

09/01/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10
Reduced Emissions 30

Bond Funding Cost
Adopted:
$462,271
Current Approved:
$462,271
Actual Expenditures:
$462,271

Click to view the Semi-Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31