Caltrans Logo

Compressed Natural Gas (CNG) Bus Procurement

Description: 5 -40' CNG & ADA EQUIPPED BUSES

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93301
 
Senate District
16, 18
Assembly District 30, 32
Congressional District 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      16  
Increased Ridership  2      
Reduced Emissions        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
STEVE WOODS (661) 324-9874   STWOODS@ZEUA.KERN.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$1,912 $0 $1,912
PTMISEA-99314
$234 $0 $234
Non-bond Funding
Local**
$0 $0 $0
 
Total**** $2,146 $0 $2,146

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,146 $0 $2,146 $2,461 $2,461 $-315
 
Total* $2,146 $0 $2,146 $2,461 $2,461 $-315

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
02/21/2011 

02/21/2011 
03/09/2010 

09/15/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2010 

05/15/2010 
02/21/2011 

02/21/2011 
09/01/2010 

09/30/2010 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 16
Increased Ridership 2
Reduced Emissions

Bond Funding Cost
Adopted:
$2,146,218
Current Approved:
$2,146,218
Actual Expenditures:
$2,146,218

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31