Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Compressed Natural Gas (CNG) Bus Procurement |
Description: 5 -40' CNG & ADA EQUIPPED BUSES
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Kern |
City | Bakersfield |
Zip Code | 93301 |
Senate District |
16, 18 |
Assembly District | 30, 32 |
Congressional District | 22 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 16 | |
Increased Ridership | 2 | |
Reduced Emissions |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
STEVE WOODS | (661) 324-9874 | STWOODS@ZEUA.KERN.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $0 | $0 | ||||
PTMISEA-99313 |
$1,912 | $0 | $1,912 | ||||
PTMISEA-99314 |
$234 | $0 | $234 | ||||
Non-bond Funding | |||||||
Local** |
$0 | $0 | $0 | ||||
Total**** | $2,146 | $0 | $2,146 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$2,146 | $0 | $2,146 | $2,461 | $2,461 | $-315 | |
Total* | $2,146 | $0 | $2,146 | $2,461 | $2,461 | $-315 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
|
02/21/2011 02/21/2011 |
03/09/2010 09/15/2010 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
04/01/2010 05/15/2010 |
02/21/2011 02/21/2011 |
09/01/2010 09/30/2010 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 16 | |
Increased Ridership | 2 | |
Reduced Emissions |
Bond Funding Cost | |
---|---|
Adopted: |
$2,146,218 |
Current Approved: |
$2,146,218 |
Actual Expenditures: |
$2,146,218 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31