Caltrans Logo

Purchase New Transit Bus

Description: PUCHASE 1 10 PASSENGER PARA TRANSIT BUS

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Taft
Zip Code 93268
 
Senate District
18
Assembly District 32
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  10      
Reduced Operating/Maintenance Cost  40      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
TERESA STATLER (661) 763-1350   TSTATLER@CITYOFTAFT.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$40 $0 $40
PTMISEA-99314
$15 $0 $15
Non-bond Funding
Local**
$0 $12 $12
 
Total**** $54 $12 $66

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$54 $12 $66 $66 $66 $0
 
Total* $54 $12 $66 $66 $66 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/31/2009 

03/31/2009 
05/04/2010 

05/04/2010 
12/04/2008 

05/19/2009 
100   

 


Begin Closeout Phase

End Closeout Phase
03/31/2010 

06/30/2010 
05/04/2010 

05/04/2010 
06/01/2009 

04/15/2010 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 10
Reduced Operating/Maintenance Cost 40

Bond Funding Cost
Adopted:
$54,432
Current Approved:
$54,432
Actual Expenditures:
$54,432

Click to view the Semi-Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31