Caltrans Logo

Bus Rehab Program

Description: Rehab up to 373 buses of LACMTA's fleet

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code 90012
 
Senate District
17, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 32
Assembly District 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  17    17  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
EMMA NOGALES (213) 922-3066   NOGALESE@METRO.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$1,143 $-302 $841
PTMISEA-99313
$41,484 $-24,997 $16,487
PTMISEA-99314
$2,370 $0 $2,370
Non-bond Funding
Local**
$9,297 $-5,003 $4,294
 
Total**** $54,294 $-30,303 $23,991

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$54,294 $-30,303 $23,991 $19,698 $19,698 $4,294
 
Total* $54,294 $-30,303 $23,991 $19,698 $19,698 $4,294

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
 

12/28/2011 
07/01/2008 

08/30/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
03/09/2011 

12/28/2011 
09/01/2011 

10/25/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 17 17

Bond Funding Cost
Adopted:
$44,997,000
Current Approved:
$18,856,705
Actual Expenditures:
$18,856,705

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31