Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Bus Rehab Program |
Description: Rehab up to 373 buses of LACMTA's fleet
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Los Angeles |
Zip Code | 90012 |
Senate District |
17, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 32 |
Assembly District | 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58, 59, 60, 61 |
Congressional District | |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 17 | 17 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
EMMA NOGALES | (213) 922-3066 | NOGALESE@METRO.NET |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$1,143 | $-302 | $841 | ||||
PTMISEA-99313 |
$41,484 | $-24,997 | $16,487 | ||||
PTMISEA-99314 |
$2,370 | $0 | $2,370 | ||||
Non-bond Funding | |||||||
Local** |
$9,297 | $-5,003 | $4,294 | ||||
Total**** | $54,294 | $-30,303 | $23,991 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$54,294 | $-30,303 | $23,991 | $19,698 | $19,698 | $4,294 | |
Total* | $54,294 | $-30,303 | $23,991 | $19,698 | $19,698 | $4,294 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
|
12/28/2011 |
07/01/2008 08/30/2011 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
03/09/2011 12/28/2011 |
09/01/2011 10/25/2011 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 17 | 17 |
Bond Funding Cost | |
---|---|
Adopted: |
$44,997,000 |
Current Approved: |
$18,856,705 |
Actual Expenditures: |
$18,856,705 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31