Caltrans Logo

Install Frangible Tables in Metrolink Rail Cars for Enhanced Safety

Description: Installation of 8 frangible tables in up to 35 Metrolink rail cars to improve the safety of the passengers seated in the cars in the event of a collision.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code 90012
 
Senate District
18, 19, 20, 21, 22, 23, 24, 25, 27, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38
Assembly District 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 48, 49, 50, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80
Congressional District 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 34, 38, 39, 40, 41, 42, 43, 44, 47, 48, 49
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20    20  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
FRANK FLORES (213) 922-2456   FLORESF@METRO.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99314
$500 $0 $500
Non-bond Funding
State/Federal*
$0 $830 $830
 
Total**** $500 $830 $1,330

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $500 $500 $-500
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$500 $830 $1,330 $0 $0 $1,330
 
Total* $500 $830 $1,330 $500 $500 $830

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
 

 
07/01/2009 

06/01/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
03/14/2011 

02/21/2013 
02/01/2012 

11/14/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20 20

Bond Funding Cost
Adopted:
$500,000
Current Approved:
$500,000
Actual Expenditures:
$500,000

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31