Gold Country Stage-Transit Transfer Center

Description: Implementation of a new Transit Transfer Center

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Nevada
City Nevada City
Zip Code 95959
 
Senate District
04
Assembly District 03
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    10  
Increased Ridership      10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SUSAN HEALY-HARMAN (530) 477-0103   SUSAN.HEALY-HARMAN@CO.NEVADA.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $18 $18
PTMISEA-99313
$21 $297 $318
PTMISEA-99314
$0 $45 $45
Non-bond Funding
State/Federal*
$480 $0 $480
 
Total**** $501 $360 $861

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$40 $-8 $32 $32 $32 $0
Design(PS&E)
$65 $65 $130 $130 $130 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$396 $303 $699 $699 $699 $0
 
Total* $501 $360 $861 $861 $861 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
02/23/2009 

02/23/2009 
12/01/2009 

02/01/2010 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
02/23/2009 

02/23/2009 
02/01/2009 

04/01/2009 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
02/23/2009 

02/23/2009 
02/01/2009 

12/01/2009 
100   

 


Begin Construction Phase

End Construction Phase
 

 
09/11/2012 

02/15/2013 
09/01/2011 

04/30/2013 
90   

 


Begin Closeout Phase

End Closeout Phase
11/30/2010 

12/31/2010 
02/15/2013 

02/15/2013 
04/30/2013 

06/30/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 10
Increased Ridership 10

Bond Funding Cost
Adopted:
$21,000
Current Approved:
$362,901
Actual Expenditures:
$362,901

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31