CCCTA Rolling Stock Replacement

Description: Project is to fund replacement of 40 full size transit coaches that have reached the end of their useful life

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa
City Concord
Zip Code 94520
 
Senate District
07
Assembly District 11
Congressional District 07
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  8      
Reduced Operating/Maintenance Cost  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
CELINDA DAHLGREN (925) 676-1976   CDAHLGRAN@CCTA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $9 $9
PTMISEA-99313
$1,491 $305 $1,796
PTMISEA-99314
$480 $0 $480
Non-bond Funding
State/Federal*
$16,901 $-2,634 $14,267
Local**
$0 $1,674 $1,674
 
Total**** $18,873 $-646 $18,227

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$18,873 $-646 $18,227 $18,227 $18,227 $0
 
Total* $18,873 $-646 $18,227 $18,227 $18,227 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/01/2009 

09/01/2009 
10/20/2011 

10/20/2011 
03/01/2009 

05/01/2009 
 

 


Begin Closeout Phase

End Closeout Phase
02/01/2009 

03/30/2011 
10/20/2011 

02/21/2013 
05/01/2010 

03/01/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 8
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
$1,971,591
Current Approved:
$2,276,737
Actual Expenditures:
$2,276,737

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31